🏠 Costs · Full renovation

Full apartment renovation cost in Spain in 2026

How to estimate a full apartment renovation without relying only on a price per square metre: services, bathrooms, kitchen, windows and quality.

Reading time9 min
LevelIntermediate
TypeFull renovation
Key ideaPrice per m² is a useful reference, but bathrooms, kitchen, windows and layout changes must be counted separately.
IN 30 SECONDS

Budget the full specification, not just floor area

  • A full renovation should not be reduced to one €/m² figure.
  • In the BricoDato example for 80 m², a full standard renovation with one bathroom and a full kitchen, the reference is about €57,960 and the range about €45,790–€75,930.
  • Layout changes, complete service replacement, extra bathrooms or new windows can move the budget substantially.
01 · LEARN

What “full renovation” actually means

It can include demolition, building work, electrics, plumbing, climate systems, floors, walls, paint, joinery, bathroom, kitchen and windows. The label “full” does not guarantee every item is included; read the actual scope.

02 · LEARN

Indicative example for an 80 m² apartment

In the BricoDato estimator, an 80 m² home, full renovation with services, standard quality, one full bathroom and kitchen included gives a reference close to €57,960. The example range is approximately €45,790–€75,930.

This example excludes professional design fees, permits, asbestos, structural strengthening and temporary accommodation.
03 · LEARN

Why a price per m² can mislead

Two 80 m² apartments can have one or two bathrooms, very different kitchens, five or twelve windows and services that are reusable or completely obsolete. €/m² is useful for scale, not for a final comparison.

04 · LEARN

Where unforeseen work appears

  • Old hidden services.
  • Uneven or damaged substrates.
  • Damp or water ingress.
  • Structural elements limiting layout changes.
  • Joinery and cabinetry lead times.
  • Building rules, permits and waste requirements.
05 · LEARN

How to keep the budget under control

Define a specification, freeze major decisions before work starts, agree how changes are priced and use payment milestones linked to progress. Keep contingency for genuine unknowns, not for choices that could have been decided earlier.

06 · LEARN

What documents to ask for before choosing

For a large project, look for measurements, line items, material specification, programme, payment terms, exclusions and responsibilities. Layout changes, complex services or structural work may require specific technical input.

COMMON QUESTIONS

Frequently asked questions

How long can a full renovation take?

It can take several weeks or months depending on area, layout changes, services, procurement and trade coordination.

Should I keep a contingency budget?

Yes. Renovation work can reveal hidden conditions. The estimator lets you add a contingency to the high end of the range.

Is €/m² enough to compare quotes?

No. It is useful for initial scale, but kitchens, bathrooms, windows, services and finish level should be compared as line items.

NEXT STEP

Continue with these tools

PRACTICAL DECISION GUIDE

Build a renovation budget around scope, not only m²

A full renovation can mean cosmetic finishes or replacement of major services. Compare floor plans, wet areas, installations and finish quality first; only then do floor-area benchmarks become meaningful.

Example to adapt

For a hypothetical 80 m² apartment, list each room separately and identify electrical points, plumbing alterations, window changes, wall repairs and demolition. Prepare three columns — essential, optional and deferred — so that scope changes can be tracked without mistaking them for cost inflation.

Budget sectionClarify before costingTypical missed item
Demolition and disposalWhat is removed and carried outPermits, containers or access
ServicesElectrical, water and ventilation scopeOutdated or inaccessible runs
FinishesSurfaces, brands, labour scopePreparation or transitions

Checks before acting

  • Set a documented priority list before soliciting real external professional quotes.
  • Keep a contingency based on project risk rather than assuming every building is identical.
  • Request a written schedule and staged payments tied to deliverables.
  • Identify work affecting structure, shared services or regulated installations early.
Important: No general €/m² example replaces an inspection and current offers. Structural and regulated work must be designed or performed by qualified professionals.

Keep a useful record: Keep room-by-room scope, quantities, specifications, contingency assumptions and approved changes.

Project control · Eighty-square-metre example

Control changes before you close up walls and floors

Two apartments with the same floor area can need very different service replacements and repairs. During a full renovation, the most useful document is not just the original €/m² number: it is the current approved scope, cost forecast and work sequence.

Illustrative change-order arithmetic

Suppose an initial accepted scope costs €58,000. An identified concealed-service repair approved at €2,600 raises the forecast to €60,600. Removing €1,400 of optional work through a written agreed credit brings it to €59,200. Do not assume a credit exists until the contractor confirms it.

Figures are invented and should be compared on the same basis for VAT and exclusions.

Keep three sets of records

Use the dated floor plan and room-by-room specification, an itemised change register signed off before changes where possible, and a record of completed work and tests. Photograph concealed work only when safe and authorised.

Three checkpoints that prevent expensive uncertainty

  1. Before demolition: document existing services, structural questions, access restrictions, permits and the boundaries of work. Qualified specialists must assess safety-critical changes.
  2. Before closing walls or floors: confirm concealed installations and applicable inspection/test requirements; retain the results and locations.
  3. Before final payment and handover: review the agreed snagging list, manuals, warranties, measurements and the payment schedule against delivered work.

A planning allowance should not be used to approve unassessed structural alterations, hazardous-material removal or fixed gas/electrical work. Seek suitable professional design and site supervision.

Use the renovation cost calculator for early sensitivity estimates, not as a substitute for priced contract documents.